PXIE LEBT Commissioning Status

Document #:
Project X-doc-1308-v1
Document type:
talk
Submitted by:
Lionel R Prost
Updated by:
Lionel R Prost
Document Created:
29 Jul 2014, 16:16
Contents Revised:
29 Jul 2014, 16:16
DB Info Revised:
29 Jul 2014, 16:16
Viewable by:
  • Public document
Modifiable by:
Abstract:
Update on the status of the PXIE LEBT construction and beam measurements.
Emittance measurements with the 'donut' and the emittance scanner are shown for the beam line configuration with one solenoid. During the July shutdown, the last 2 solenoids were added, as well as an ecool BPM, which will serve as a clearing electrode.