Project X-doc-# Title Author(s) Topic(s) Last Updated
1370-v3 The PIP-II Reference Design Rep Valeri A Lebedev Reports
Linac
Main Injector
21 May 2015
1274-v2 Preparation for the PIP-II RDR Valeri A Lebedev LE Linac
Presentations
Main Injector
01 Apr 2014
776-v7 Reference Design Report Russ Alber et al. Controls
Absorbers
Reports
Instrumentation
Linac
Recycler
Transfer Line
Conventional Facilities
Cryogenics
Main Injector
17 Jul 2013
1105-v1 Project X Siting Workshop Presentations - October 2012 Russ Alber et al. Experiments
Transfer Line
Conventional Facilities
Main Injector
05 Oct 2012
957-v2 Electron Cloud Experiments Robert M. Zwaska Instabilities
Main Injector
03 Nov 2011
815-v1 Ecloud: A quick check of the microwave method with obstructions ("ears") in MI beam pipe Cheng-Yang Tan Main Injector
03 Feb 2011
763-v1 MI Magnetic Field Measurements Cheng-Yang Tan Main Injector
21 Oct 2010
762-v1 Proposal to test TiN at SPS Cheng-Yang Tan Main Injector
21 Oct 2010
758-v1 The Ecloud Measurement Setup in the Main Injector Cheng-Yang Tan et al. Experiments
Main Injector
13 Oct 2010
745-v1 Main Injector/Recycler Ioanis Kourbanis Recycler
Main Injector
09 Sep 2010
686-v1 Recent MI Results on TiN and C Coated Beam Pipes Robert M. Zwaska Main Injector
08 Sep 2010
739-v1 RF Simulations and Analysis for the Project-X Main Injector Cavity Liling Xiao MI RF
08 Sep 2010
687-v1 Electron Cloud Modeling for the Main Injector Paul Lebrun et al. Simulations
Main Injector
08 Sep 2010
738-v1 Space Charge Simulations for MI Robert D Ryne Main Injector
08 Sep 2010
670-v1 MI Simulations with SYNERGIA Eric G Stern Simulations
Space Charge Effects
Main Injector
08 Sep 2010
730-v1 Progress and Plans on MI beam Pipe Coatings David P Capista et al. Instabilities
Main Injector
07 Sep 2010
668-v1 Introduction Ioanis Kourbanis Main Injector
07 Sep 2010
671-v2 Preparation of Intense Bunches at MI 8 GeV Kiyomi Seiya Main Injector
07 Sep 2010
722-v1 ICD-2 Overview Sergei Nagaitsev Linac
Recycler
Main Injector
07 Sep 2010
683-v1 New MI Cavity Progress and Plans 2010 Joseph E Dey MI RF
07 Sep 2010
405-v1 Specifications for the Proton Driver Injection Absorber David E. Johnson Proton Driver
Main Injector
31 Jan 2010
417-v1 2 MW Upgrade of the Fermilab Main Injector Weiren Chou Main Injector
20 Jan 2010
416-v1 Lifetime of Stark States Hydrogen Atom in Magnetic Field Calculation and Estimation of Losses at Stripping Injection Alexandr Drozhdin et al. Presentations
RCS
Main Injector
20 Jan 2010
422-v1 Test of New Stripping Foils in the Booster Weiren Chou et al. RCS
Main Injector
20 Jan 2010
421-v1 Overview of proton drivers for neutrino super beams and neutrino factories Weiren Chou Presentations
Linac
RCS
Main Injector
20 Jan 2010
420-v1 High energy H- ion transport and stripping Weiren Chou Linac
RCS
Main Injector
20 Jan 2010
419-v1 8 GeV H- ions: transport and injection Weiren Chou Linac
RCS
Main Injector
20 Jan 2010
515-v1 ECloud status meeting, Fall-Winter 09 Paul Lebrun Instabilities
Main Injector
17 Dec 2009
524-v1 The SEY Test Stand Robert M. Zwaska Instabilities
Main Injector
17 Dec 2009
329-v1 ICD-2: Next Step in the Process Valeri A Lebedev RCS
H- Injection
Main Injector
25 Nov 2009
257-v4 Status of the MI rf R&D effort Joseph E Dey MI RF
Main Injector
28 Oct 2009
293-v1 MI and RR Rings, Wworking Group Report Ioanis Kourbanis Recycler
Main Injector
12 Sep 2009
288-v1 TiN Coating at SLAC Uli Wienands Main Injector
12 Sep 2009
289-v1 Space Charge Simulations at Berkeley Ji Qiang Recycler
Main Injector
12 Sep 2009
290-v2 Cavity Simulations in SLAC Liling Xiao MI RF
12 Sep 2009
281-v2 MI/RR Space Charge Simulations with Synergia James F Amundson et al. Simulations
Presentations
Collaboration
Space Charge Effects
Main Injector
11 Sep 2009
280-v1 MI/RR RIngs. Introduction/Update Ioanis Kourbanis Recycler
Main Injector
11 Sep 2009
272-v1 Electron Cloud Experimental Upgrade in the Main Injector Cheng-Yang Tan et al. Instabilities
Main Injector
11 Sep 2009
256-v1 Status of Microwave Measurements in the Main Injector Nathan Eddy Instrumentation
Main Injector
10 Sep 2009
269-v1 Status of Ecloud Build-Up Simulations for the FNAL MI- Sept. 2009 Miguel A Furman Instabilities
Main Injector
10 Sep 2009
267-v1 Titanium Nitride Magnetron Sputtering Linda Valerio Main Injector
10 Sep 2009
160-v0 Item 1.4.6 - BoE for CD-0 Director's Cost Review Ioanis Kourbanis Directors Reviews
Basis of Estimate
Main Injector
04 Mar 2009
83-v2 Initial Configuration Document v1.1 Russ Alber et al. Controls
Absorbers
Reports
HE Linac
Instabilities
Instrumentation
LE Linac
Project Management
HINS
Space Charge Effects
Transfer Line
Conventional Facilities
Cryogenics
H- Injection
Main Injector
16 Mar 2009
180-v1 PX_MI_RR_directors_review Ioanis Kourbanis Directors Reviews
Basis of Estimate
Main Injector
13 Mar 2009
174-v1 Main Injector and Recycler RF Joseph E Dey Directors Reviews
Basis of Estimate
Recycler
Main Injector
13 Mar 2009
178-v1 Project X: Initial Configuration Paul Derwent Controls
Directors Reviews
Instrumentation
Presentations
Linac
HINS
Recycler
Transfer Line
Conventional Facilities
Cryogenics
Main Injector
13 Mar 2009
149-v2 RD&D Plan from ICD Russ Alber et al. Controls
Reports
Instrumentation
Linac
HINS
Recycler
Transfer Line
Conventional Facilities
Cryogenics
H- Injection
Main Injector
11 Mar 2009
132-v1 Main Injector Working Group Report Ioanis Kourbanis et al. Reports
Main Injector
24 Feb 2009
124-v1 MI Collimation experience Bruce C. Brown Presentations
Main Injector
24 Feb 2009
123-v1 Review of MI e-cloud simulations Miguel A Furman Presentations
Main Injector
24 Feb 2009
122-v1 MI e-cloud measurements Robert M. Zwaska Presentations
Main Injector
24 Feb 2009
107-v1 Experience with the RHIC yt-jump system Thomas Roser Presentations
Main Injector
24 Feb 2009
105-v1 Review of MI Issues Ioanis Kourbanis Presentations
Main Injector
24 Feb 2009
106-v1 New rf system requirements/preliminary design John S Reid Presentations
Main Injector
24 Feb 2009
497-v1 Measurements of Electron Cloud Density by Microwave Transmission Manfred Wendt Instabilities
Instrumentation
Main Injector
08 Dec 2008
76-v1 Project X Main Injector Valeri A Lebedev Presentations
Reviews
Main Injector
07 Oct 2008
60-v1 Modeling of Ring Performance Robert D Ryne Simulations
Presentations
Recycler
Main Injector
01 Oct 2008
59-v1 Injection and Extraction David E. Johnson Presentations
Recycler
Transfer Line
Main Injector
01 Oct 2008
58-v1 Transverse Damper Phil Adamson Instabilities
Presentations
Recycler
Main Injector
01 Oct 2008
57-v1 RF System and Beam Loading Compensation John S Reid Presentations
Recycler
Main Injector
01 Oct 2008
56-v1 Transition Crossing Simulations Ioanis Kourbanis Simulations
Presentations
Main Injector
01 Oct 2008
55-v1 Gamma Transition Jump Weiren Chou et al. Presentations
Main Injector
01 Oct 2008
54-v1 Present MI Operation and Near Future Plans Ioanis Kourbanis Operations
Presentations
Main Injector
01 Oct 2008
50-v1 Beam Loss and Collimation Nikolai Mokhov Absorbers
Presentations
Main Injector
01 Oct 2008
49-v1 Electron Cloud, EP Instability and Requirements for Vacuum Miguel A Furman Instabilities
Presentations
Recycler
Main Injector
01 Oct 2008
48-v1 Theoretical Expectations for Instabilities Alexey V Burov Instabilities
Presentations
Recycler
Main Injector
01 Oct 2008
47-v1 Experimental Observations of Instabilities at Main Injector Ioanis Kourbanis Instabilities
Presentations
Main Injector
01 Oct 2008
46-v1 SNS Ring Beam Status Slava Danilov Other Labs
Main Injector
01 Oct 2008
23-v1 Main Injector Overview Valeri A Lebedev Presentations
Main Injector
30 Sep 2008
5-v1 Project X ICD: High-energy linac parameters Sergei Nagaitsev Controls
Linac
Conventional Facilities
Cryogenics
H- Injection
Main Injector
29 Aug 2008
536-v1 Electron Cloud Instabilities Robert M. Zwaska Instabilities
Main Injector
06 Dec 2006

Number of documents found: 71

DocDB Home ]  [ Search ] [ Last 20 Days ] [ List Authors ] [ List Topics ]

--------
Security, Privacy, Legal
Fermilab Policy on Computing
Fermi National Accelerator Laboratory

For assistance contact HelpDesk



DocDB Version 8.7.23, contact Document Database Administrators
Execution time: 1 wallclock secs ( 0.28 usr + 0.02 sys = 0.30 CPU)